BEND, Ore. (KTVZ) — In this article is the ODOT Region 4 building report for the 7 days of July 20-23.

The Oregon Department of Transportation is dedicated to offering a risk-free, effective transportation procedure. ODOT invests in Oregon’s long run by way of roadway advancement tasks. The following initiatives are found in just ODOT’s Region 4 encompassing Central Oregon from The Dalles to Klamath Falls on the east facet of the Cascades.

All work is dependent on weather disorders, and schedules are topic to change.

Deschutes County

U.S. 97: S Century Drive to USFS border (MP 153.11-MP 156.26)

The contractor will be preparing the web page for Fireplace Season Level 4 Operational Shut Down. No predicted delays to targeted visitors are predicted.

U.S. 97: Nels Anderson Place-Romaine Village Way (Bend Parkway Repaving

No get the job done on this job is prepared this week.

For a lot more information, which includes detour maps, make sure you stop by the job site.

Harney/Lake counties

US395: Massive Stick – Alkali Lake, Lakeview, Lakeview-Burns Highway (MP 15.43- MP46.93).

No get the job done scheduled the 7 days of July 20. Do the job will resume July 26.

US395 & OR140 (Lakeview) ADA Suppress Ramps (MP142.62-MP144.06) Demolition, excavation and sidewalk perform is scheduled. Flagging procedure at situations with nominal delays to site visitors.

Hood River County

I-84: Hood River Eastbound & Westbound Bridges venture, I-84 (MP 63.9-64.42)

Contractor has accomplished the Hood River Bridges Undertaking, this will likely by the final entry on the building report.

For much more details, you should take a look at the project venture site.

Jefferson County
and CTWS Reservation

U.S. 26: Warm Springs Security Corridor, (MP 103.02-MP111.16).

The contractor will carry out excavation and earthwork routines.  New curb and drainage pipes will also be put in alongside the shoulder of the highway.  The freeway will be lessened to one journey lane which will be controlled by flaggers and a pilot car or truck.  Targeted visitors can anticipate delays of up to 20 minutes.

Klamath County

OR39: Crest St. – Madison St., Klamath Falls, MP2.99-MP4.26) Cleanup do the job is scheduled through the day. No delays envisioned.

OR140 Brett Way Extension (South Klamath Falls Highway, MP3.74-4.75)

Survey and excavation get the job done is scheduled to start off. Assume small delays. Homedale is shut at the intersection of South Klamath Falls Highway and Homedale. Use signed detour route.

Sherman County

U.S. 97: Rockfall Venture (U.S. 97/Sherman Highway milepost .87-3.69)

Contractor will execute corrective indication function below shoulder.

Wasco County (OR)/Klickitat (WA)

The Dalles (Columbia River) Bridge Job (U.S. -197: WA MP .57 I-84: MP100.6-U.S. 197:OR  MP .61 I-84: MP 102.2.

Development crews will be functioning overnight (Sun – Thur nights) anticipate delays up to 20 minutes during nighttime hrs whilst flaggers manage visitors throughout the bridge. The bulk of work will occur under the bridge and features ending scaffolding do the job and set up of a trolley platform. Crews will keep on forming new concrete panels at their pre-cast yard area.

Wasco County/CTWS Reservation

US26: Crystal clear Lake Highway – NW Dogwood Lane, Heat Springs Freeway, (MP 66.43-112.91).

Assume lane closures with flagging as contractor eliminates and installs stormwater inlets and pipes concerning milepost 66 and milepost 71.

Wheeler County

U.S.26: Bridge Creek Bridge Venture (U.S. 26/Ochoco Highway, milepost 64.91-65.19)

Contractor is doing streambed reconstruction and earthwork. Website traffic is routed to a solitary lane detour future to the current bridge, and managed by a traffic signal.